Vibration Assessment of Subway Line 2

Project Overview
  • A new building is planned near the operation section of Subway Line 2.
  • Review of vibration and structure-borne noise within the office facility caused by subway operation.
  • Comparison with recommended vibration/noise criteria and application of anti-vibration measures if exceeding limits.
  • Application of anti-vibration measures using HD-MAT-50T (Slurry Wall method applied).
  • Vibration/noise levels satisfied recommended criteria after implementation of anti-vibration measures.
Current Condition Prediction
  1. Vibration Prediction

  2. Structure-Borne Noise Prediction

Vibration Isolation Measures

Installation of vibration isolation mats in the minimum required area after considering cost-efficiency

 

 

Prediction After Vibration Isolation Measures
  1. Vibration Prediction

  2. Structure-Borne Noise Prediction

Vibration Isolation Installation

Installation of Vibration Isolation Mats in Slurry Wall Sections

 

 

  1. STEP 01

    Attaching the vibration isolation frame to the rebar cage

  2. STEP 02

    Hoisting the rebar cage with vibration isolation mats

  3. STEP 03

    Hoisting for diaphragm wall insertion

  4. STEP 04

    Insertion Process 1

  5. STEP 05

    Insertion Process 2

  6. STEP 06

    Insertion Completed: Concrete placement to follow